SXSW Fall 2026 Construction Update

SXSW Construction Update: New Heights, New Milestones and Continued Progress

Big changes are happening at SXSW, as Hillmont enter a new stage of development. From window installations and interior finishes to shared amenities and landscaping, the latest updates offer a look at how this growing Vaughan community is coming to life.

Reaching New Heights: Hillmont (Towers 3 & 4)

Crews are now working on the Mechanical Penthouse (MPH), one of the final components of the towers' main concrete structures. Expected to be completed by the end of November 2026, this work represents an important step toward structural completion.

On the exterior, window installation is now complete at Tower 4, while Tower 3 has reached the 25th floor. As the buildings become increasingly enclosed, interior construction can advance while the towers' architectural design becomes more defined.

Inside the Towers: Bringing Residential Suites to Life

Inside both towers, work is shifting toward the details that will define each residential suite.

Kitchen installations have begun, introducing some of the first finishing elements within the homes. Drywall installation has also reached approximately one-third of the way up both buildings, establishing individual suite layouts and interior spaces.

Plumbing rough-ins are nearing completion, preparing the suites for the installation of final fixtures and finishes.

Shared Amenities: Spaces Coming Together

Hillmont's shared amenity spaces are entering the next stage of interior construction, with drywall installation now complete and millwork underway.

The addition of custom cabinetry, built-in features and architectural details will help define the look and functionality of these spaces, bringing the community's thoughtfully designed amenities closer to their finished form.

Landscaping Progress: Shaping the Outdoor Experience

Outside the towers, landscaping is transforming the surrounding grounds and shared outdoor areas.

Landscaping around the amenity spaces is nearly complete, while work has now begun at ground level, extending improvements across the development.

These outdoor areas will help connect the residential towers and shared amenities, creating welcoming spaces that complement the overall community design.

Watch the latest community update here:


Looking Ahead at SXSW

With structural work approaching completion and interior installations advancing, Hillmont is entering an exciting period of construction.

In the months ahead, attention will remain on residential finishes, shared amenities and landscaping as Towers 3 and 4 move through their next phases of development.

Stay tuned for future updates as we continue to share the latest from SXSW.

Discover more about SXSW and explore everything this Vaughan community has to offer on our website here.